News

Trolley bus line extension

Electro Sistem is the general entrepreneur of the trolley bus contact line network extension in Baia Mare. The project is under execution and the extension of the trolley bus line requires the following works: “ building of the 5,1 km long, double path, contact network;

“ building of a 660Vcc rectification station;

“ direct current supply of the contact network (supply cables);

“ power supply for the rectification station;

“ deflection and protection of existing urban networks;

“ providing the utilities for the rectification station;

“ procurement of equipment for the rectification station as well as the one for the substation.

The conclusion of works is forecasted for June, 2014.